VIEW ALLWould a law compelling the Contractor to purchase those masks, install those sanitising stations or checkpoints, implement social distancing, etc. change that causal link? From one point of view, arguably not.
Sub-Clause 13.7[10] applies to increases and decreases in Cost resulting from a change in legislation which affects the Contractor in its performance of its obligations under the Contract. A Sub-Clause 13.7[11] claim is only available where the Contractor suffers (or will suffer) delay and/or loss as a result of changes in legislation. In the scenario above, the Contractor would implement the necessary measures regardless of whether a new law requiring them comes into force. Also, had the coronavirus not emerged, the new law would have never existed. That is, the two events are not independent from each other because the pandemic caused the relevant new law to come into force. Therefore, insofar as a new law compels the Contractor to do something that the Contractor would have done regardless (of the coming into force of such new law and of the legal implications of non-compliance), then such new law, it may be argued, does not cause the increases in Cost and/or delay that result from the implemented measures.
In other words, the new law fails the “but for” test. This test is used to determine the cause of a loss as a matter of fact. In the context of this article, the test is: would the loss or delay have happened but for the occurrence of an act or event? Put another way: if the act or event had not occurred, would the loss or delay have been suffered? As such, if the loss or delay hinge on the act or event (e.g., the new law), it passes the test in that the act or event is a proven cause in fact of the loss or delay. However, if the loss or delay would have been suffered even without the act or event (such as in the scenario above), it fails the test. Therefore, under the interpretation above, Sub-Clause 13.7[12] would not apply.
As a result, the Contractor would not be able to claim time and money via Sub-Clause 13.7[13] but may perhaps still be entitled to time, for example, under Sub-Clause 19.4 (a)[14]. In the scenario above, Covid-19 would pass the “but for” test. Therefore, subject to meeting all other requirements for a Sub-Clause 19.4 (a)[15] claim,[16] if the Contractor can prove that it has suffered delay by reason of a Covid-19 event or circumstance, it should be entitled to an extension of time.
Perhaps a different scenario would put this into more perspective. If a Contractor were building a pier in the Caribbean and a hurricane was imminent, would it wait for the government to tell everyone to seek shelter before closing operations and sending everyone home? Of course not. That would be irresponsible. Some may argue that this situation is different because most Caribbean countries have had laws for decades that allow them to order businesses to close down if a hurricane is imminent and therefore Sub-Clause 13.7[17] would never apply. However, the relevant question for the purposes of this analogy is not whether a law is new. As mentioned before, the issue is causation and, in that sense, the hurricane scenario is no different from the pandemic scenario.
Also consider the scenario where a Contractor purchases surgical masks to protect its personnel on Site from Covid-19 and they are used before the legislature of the Country makes a new law that requires the use of masks. In this situation, the masks are purchased and used before the law comes into force. Therefore, the Cost incurred in the purchase of such masks could not be said to have resulted from the change in legislation.
However, once the law comes into force, questions arise:
According to the interpretation presented above, it may be arguable that, in either case, the cause of the purchase and use of the masks does not change insofar as Covid-19 continues to be a threat in the eyes of the Contractor. In fact, the Contractor’s purchase of the masks prior to the enactment of the new law may indicate that the Contractor would continue purchasing the masks regardless of the existence of a new law requiring them.
To make matters more complex, the legislature of a Country may have different views on what constitutes appropriate measures. It may pass new laws that go beyond what a Contractor considers necessary. For example, the new law may require the masks to be type KN95 but the Contractor intended to purchase the less expensive surgical masks. According to the interpretation presented above, in such a scenario, the Contractor may have an arguable case under Sub-Clause 13.7[20] but, it is suggested, only to the extent of the difference in Cost between the KN95 masks and the cheaper masks, not for the entire Cost of the KN95 masks. That is, the increase in Cost that results from purchasing the KN95 masks would arguably be caused by the new law and the Contractor may be able to claim the difference in Cost between the two types of masks.
Whether a Contractor is entitled to Cost under Sub-Clause 13.7[29] in Covid-19 scenarios will depend on many issues, including the presence of pre-existing obligations and the interpretation given to whether the complexities in the causal link are relevant to its application.
However, at the end of the day, what really matters is not why a Contractor or an Employer take care of the health and safety of the personnel on Site during the pandemic, but that they do so quickly and effectively insofar as they possibly can to avoid the worst of the effects of the virus on the people who come to work. Questions of who is at risk for any Cost and delay suffered are to be dealt with when time allows (though within the timeframes in Clause 20 and other relevant Clauses).
When that time arrives, Parties, Engineers, DABs/DAABs and arbitral tribunals should give serious thought to the particular facts of each claim and how they relate to questions of causation, risk and pre-existing obligations in light of the relevant Contract provisions and the law, old and new.
[1] Partially reworded in FIDIC 2017 to [Adjustments for Changes in Laws] and renumbered to Sub-Clause 13.6.
[2] In the context of FIDIC 1999/2017, this may potentially be Sub-Clause 8.4/8.5 [Extension of Time for Completion], Sub-Clause 8.5/8.6 [Delays Caused by Authorities], and Sub-Clause 19.4 (a)/18.4(a) [Consequences of Force Majeure/an Exceptional Event].
[3] See National Highways Authority of India v Som Datt Builders-NCC-NEC (JV), Delhi High Court, Case No. OMP No. 40/2011 (25 April 2014), see https://indiankanoon.org/doc/92242211/ (accessed 24 August 2021) and National Highways Authority of India v M/S JSC Centrodorstroy, Supreme Court of India, Civil Appeal No. 2530 of 2016 (18 April 2016), see https://indiankanoon.org/doc/121392918/ (accessed 24 August 2021).
[4] Or Sub-Clause 13.6 under FIDIC 2017.
[5] Court cases and arbitral awards about Sub-Clause 13.7 are scarce and there are very few commentators that delve into the Sub-Clause to any depth, such as: Ellis Baker et al, FIDIC Contracts: Law and Practice, ¶ 2.160-2.163 at pp 74-75 and ¶ 4.95-4.103 at pp 169-70; George Rosenberg and Andrew Tweeddale, ‘Clause 13’, FIDIC 1999 Books Clause Commentaries (2016), pp 24-26, George Rosenberg, ‘Clause 13 Variations and Adjustments’, FIDIC 2017 A Practical Legal Guide (2020), pp 340–42.
[6] Or Sub-Clause 13.6 under FIDIC 2017.
[7] For example, FIDIC 1999 and 2017 include: Sub-Clause 4.1 [Contractor’s General Obligations], Sub-Clause 4.8 [Safety Procedures] in 1999 or [Health and Safety Obligations] in 2017, Sub-Clause 6.4 [Labour Laws] and Sub-Clause 6.7 [Health and Safety] in 1999 or [Health and Safety of Personnel] in 2017. Also, applicable provisions may also be found in other documents of the Contract.
[8] Or Sub-Clause 13.6 under FIDIC 2017.
[9] Or Sub-Clause 18.4 (a) [Consequences of an Exceptional Event] under FIDIC 2017.
[10] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[11] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[12] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[13] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[14] Or Sub-Clause 18.4 (a) under FIDIC 2017.
[15] Or Sub-Clause 18.4 (a) under FIDIC 2017.
[16] Such as, for example, (1) proving that the Covid-19 event or circumstance is a Force Majeure event or circumstance under FIDIC 1999 or an Exceptional Event under FIDIC 2017, (2) proving that the Covid-19 event or circumstance prevented the Contractor from performing its obligations under the Contract, and (3) submitting the required notices.
[17] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[18] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[19] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[20] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[21] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[22] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[23] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[24] WHO, ‘Pandemic influenza’, see https://www.euro.who.int/en/health-topics/communicable-diseases/influenza/pandemic-influenza (accessed 24 August 2021) (“The most recent pandemic occurred in 2009 and was caused by an influenza A (H1N1) virus.”); WHO, ‘Past pandemics’, see https://www.euro.who.int/en/health-topics/communicable-diseases/influenza/pandemic-influenza/past-pandemics (accessed 24 August 2021) (“The first influenza pandemic of the 21st century occurred in 2009–2010 and was caused by an influenza A(H1N1) virus.”).
[25] WHO, ‘Managing epidemics: Key facts about major deadly diseases’, Geneva (2018), p 9, download from https://www.who.int/publications/i/item/managing-epidemics-key-facts-about-major-deadly-diseases (accessed 24 August 2021) (“Epidemics of infectious diseases are occurring more often, and spreading faster and further than ever, in many different regions of the world.”).
[26] WHO, ‘Pandemic influenza’, see https://www.euro.who.int/en/health-topics/communicable-diseases/influenza/pandemic-influenza (accessed 24 August 2021) (“For this reason, countries develop multi-sectoral preparedness plans describing their strategies and operational plans for responding to a pandemic.”); WHO, ‘Past pandemics’, see https://www.euro.who.int/en/health-topics/communicable-diseases/influenza/pandemic-influenza/past-pandemics (accessed 24 August 2021) (“It was the first pandemic for which many Member States had developed comprehensive pandemic plans describing the public health measures to be taken, aimed at reducing illness and fatalities.”).
[27] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[28] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.
[29] Or Sub-Clause 13.6 (a) & (b) under FIDIC 2017.